Week 8

Under-slab preparation

5855 Oakridge Trail S · Afton MN 55001

Gravel base inside the Oakridge foundation, with plumbing lines in place and the concrete safe room at the center.

In the first week of June, the crew finished preparing the base for the concrete floor. A layer of gravel was spread and leveled across the full footprint. Foam insulation was installed along the inside of the foundation walls. Plumbing lines were set in place before the pour. The walls of the concrete safe room were also complete.

The Oakridge foundation from above in June, with insulation laid for the slab.