The first Heritage build, documented.
5855 Oakridge Trail S · Afton MN 55001
Week by week.
Journal entries
Week 30Stucco
The first coat of stucco on the front of the house is finished, and the scaffolding is finally down. The final coat will wait until spring to have the best results and finish off this incredible house.
Week 30Landscaping
Landscaping has started. The beds along the house are getting a lot of evergreens and ornamental grasses, so they'll still look good in a Minnesota winter.
Week 29Exterior
The roof is finished, and most of the siding is on. We used impact-rated shingles on this house. They cost more than standard shingles, but they hold up much better in hail.
Week 23Fireplace
The Urbana fireplace is in, and it's one of our favorite things in this house. The outside stays cool enough that wood or wallpaper can go right up around it, so the surround can be almost anything.
Week 23Drywall
By the third week of September, drywall was hung in the living spaces and hallways. The crew was taping the seams and applying joint compound. The hallways include arched openings. A few walls were still open to the framing and insulation.
Week 21Entry doors and siding
As summer wound down, the front entry doors were installed. Siding installation had started on the exterior walls. Siding color samples were on site for the final selections. A tractor was working the ground near the house.
Week 17House wrap and roofing
By early August, house wrap covered the exterior walls and the roof was shingled. The house is protected from the weather, and work moves to the interior.
Week 15Windows and sheathing
In the last week of July, the exterior walls were sheathed and the windows were installed. Roof underlayment was in place over the sheathing. The interior of the house is now enclosed.
Week 13Roof trusses
The roof trusses were set by mid-July. With the trusses in place, the full height and roof shape of the house are visible for the first time. Sheathing of the walls and roof follows.
Week 12Wall framing
Wall framing was underway by the Fourth of July. The exterior walls and the main interior walls were standing on the slab. Door and window openings were framed at their final locations.
Week 10Concrete slab
The concrete slab was poured before the end of June. The lines set during under-slab preparation now extend up through the floor at their planned locations. Wall framing begins next.
Week 8Under-slab preparation
In the first week of June, the crew finished preparing the base for the concrete floor. A layer of gravel was spread and leveled across the full footprint. Foam insulation was installed along the inside of the foundation walls. Plumbing lines were set in place before the pour. The walls of the concrete safe room were also complete.
Week 6Foundation complete
The foundation was complete by Memorial Day. Soil was backfilled around the exterior walls, and the area inside the walls was filled and leveled. The next stage is preparation for the concrete floor.
Week 3Foundation walls
The foundation walls cured during the first full week of May. The house is designed for single-level living and is built slab-on-grade. A concrete safe room is included in place of a basement.
Week 2Excavation and footings
By the first of May, the building pad was graded and the footings were trenched. The driveway was cut in the same week. Materials for the foundation crew were delivered and staged on site.
Week 1Groundbreaking
Construction began in the last days of April 2026. The excavation crew arrived early in the day with an excavator and a skid steer. By the afternoon, the footprint of the house was visible from the access road. The site is five wooded acres at 5855 Oakridge Trail S in Afton.
Follow the Oakridge build by email.
Heritage Homes sends one short email when a new journal entry is published. You confirm your address first, and every email has an unsubscribe link.