The first Heritage build, documented.
5855 Oakridge Trail S · Afton MN 55001
Week by week.
Journal entries
Week 1The work begins.
April 29. The crew brought equipment in early. By afternoon the dirt was moving. The footprint of the home is now visible from the access road. What will be foundation in three weeks is right now a set of mounds and ledges. A stream and waterfall will move through these woods in time. For now the deer have it to themselves.
Week 2Foundation dug, footings prepared.
May 1. The pad is graded, footings trenched. Driveway cut, materials staged for the foundation crew next week. The shape of the house is in the dirt now, before it ever rises. Standing at the edge of the trench, you can already feel where the front door will sit.
Week 3Foundation walls, cured.
May 7. The walls cured this week. The home is shaped for single-level living, with a safe room built in instead of a basement. Walking the perimeter, the rooms have an outline you can step into. The slab comes next.